Deprecated: Return type of AdvancedAds\Abstracts\Data::offsetGet($offset) should either be compatible with ArrayAccess::offsetGet(mixed $offset): mixed, or the #[\ReturnTypeWillChange] attribute should be used to temporarily suppress the notice in /home/erudites/web/erudites.ng/public_html/wp-content/plugins/advanced-ads/includes/abstracts/abstract-data.php on line 431
If Two Charged Plates Are Maintained At A Potential Difference Of 3 Kv; The Work Done In Taking A Charge Of 600 µC Across The Field Is? - Erudites Academy

A. 0.8 J
B. 1.8 J
C. 9.0 J
D. 18.0 J

Correct Answer:

Option B = 0.8 J

Explanation

Work done = product of the charge Q, and the p.d V.
(i)/e work done = Q.V = 600 x 10-6 x 3.0 x 10-3 = 1.8 J.