Deprecated: Return type of AdvancedAds\Abstracts\Data::offsetGet($offset) should either be compatible with ArrayAccess::offsetGet(mixed $offset): mixed, or the #[\ReturnTypeWillChange] attribute should be used to temporarily suppress the notice in /home/erudites/web/erudites.ng/public_html/wp-content/plugins/advanced-ads/includes/abstracts/abstract-data.php on line 431
If A Load Of Mass 10N Stretched A Cord By 1.2cm. What Is The Total Work Done? - Erudites Academy

A. 6.0 x 10‾²J
B. 7.6 x 10‾²J
C. 1.8 x 10‾²J
D. 6.6 x 10‾²J

Correct Answer:

Option A = 6.0 x 10‾²J

Explanation

Work done on a stretched cord
= Average force x extension
= (10 + 0)/2 x 1.2 x 10‾²
= 6.0 x 10‾²J