A. average variable cost curve at its highest point
B. average cost curve at its lowest point
C. average cost curve at its lowest point
D. total cost curve at its lowest point
Correct Answer:
Option C – average cost curve at its lowest point
A. average variable cost curve at its highest point
B. average cost curve at its lowest point
C. average cost curve at its lowest point
D. total cost curve at its lowest point
Correct Answer:
Option C – average cost curve at its lowest point