Sale!

PERT Diagram Over A Gantt Chart – Critical Path

Original price was: ₦1,000.00.Current price is: ₦300.00.

Description

200 Level Computer Science exam questions and the detailed answers. Download the answers in document format. Correct, detailed, and straightforward answers.

Questions:

 

(i) List three advantages of a PERT diagram over a Gantt chart for scheduling projects.

(ii) Use Visible Analyst to create a PERT diagram for the activities shown in Figure 1.

(iii) List all paths, calculate, and determine the critical path for the projects. (20 marks)

Activity Predecessor Duration
A Conduct interview None
B Administer questionnaire A
C Read school of science reports None
D Analyse data flow B, C
E Introduce prototype B, C
F Observe reactions to prototype E
G Perform cost/benefit analysis D
H Prepare proposal F, G
I Present proposal H

 Figure 1

DOWNLOAD THE ANSWER BELOW

Copyright warnings! Do not copy.