NABTEB QUESTIONS

Describe in sequence the method of rendering an old neglected wall. – NABTEB QUESTION

ANSWER

The sequence is as follows:

(i) The brick joints should be raked out to form a key for the under coat
(ii) The surface of the wall should be made free of dirt and other things that will impair bonding.
(iii) Wet the surface with water
(iv) Apply rich mix mortar under coat
(v) Scratch the under coat to form key for the final coat.

Sunday

Share
Published by
Sunday
Tags: NABTEB

Recent Posts

EME 310 Theory Questions: Hypothesis Testing

300 Level Research Methods In Education Practice exam questions and detailed answers. Download the answers in…

3 days ago

EME 310 Theory Questions: Sampling Error And Sampling Bias

300 Level Research Methods In Education Practice exam questions and detailed answers. Download the answers in…

3 days ago

EME 310 Theory Questions: Sample And Sampling Techniques

300 Level Research Methods In Education Practice exam questions and detailed answers. Download the answers in…

3 days ago

EME 310 Theory Question: Sources Of Literature – Project Writing

300 Level Research Methods In Education Practice exam questions and detailed answers. Download the answers in…

3 days ago

EME 310 Theory Questions: Research Proposal Vs Research Abstract – Educational Research

300 Level Research Methods In Education Practice exam questions and detailed answers. Download the answers in…

3 days ago

EME 310 Theory Questions: Research Topics

300 Level Research Methods In Education Practice exam questions and detailed answers. Download the answers in…

3 days ago