Calculate the prime cost?

Given:
Stock at start:
Raw materials…………….N57 000
Work-in-progress………….N42 000
Finished goods……………N71 000

Purchase of raw materials amount to N81 000, direct labour is N38 000 and factory overhead N29 000.

A. N176 000
B. N170 000
C. N167 000
D. N156 000

Correct Answer:

Option A – N176 000

Sunday

Share
Published by
Sunday
Tags: Accounting

Recent Posts

EME 404 Theory Question: Instructional Supervisor Characteristics

400 Level Supervision Of Instruction And Accountability In Education Practice exam questions and detailed answers.…

21 mins ago

EME 404 Theory Questions: Accountability In Education

400 Level Supervision Of Instruction And Accountability In Education Practice exam questions and detailed answers.…

29 mins ago

EME 404 Theory Questions: Supervision Of Instruction And Accountability In Education

400 Level Supervision Of Instruction And Accountability In Education Practice exam questions and detailed answers.…

54 mins ago

EME 402 Theory Questions: Education Law In Nigeria

400 Level Legal Aspect Of Educational Administration Practice exam questions and detailed answers. Download the…

1 hour ago

EME 402 Theory Question: Structure And Operation Of Courts In Nigeria

400 Level Legal Aspect Of Educational Administration Practice exam questions and detailed answers. Download the…

1 hour ago

EME 402 Theory Question: Relevance Of Law In Management Of Educational System In Nigeria

400 Level Legal Aspect Of Educational Administration Practice exam questions and detailed answers. Download the…

2 hours ago